Monday, 23 January 2012

Deadlines for Thriller Project

9th Jan to 13th Jan: Thriller introduction.


16th Jan to 20th Jan: Analysis of real and student examples/ Production logos.

23rd Jan to 27th Jan: Planning and delivery of pitches.


30th Jan to 3rd Feb: Storyboarding, shot lists and other planning.

6th Feb to 10th Feb: Filming.

13th Feb to 17th Feb: Half Term.

20th Feb to 24th Feb: Filming and editing.

27th Feb to 2nd March: Filming and editing.


5th March to 9th March: 9th March Shooting deadline. 2nd lesson of this week is Rough Cut Deadline. Third lesson of week, rough cut feedback.


12th March to 16th March: End of second lesson of the week is Final Cut Deadline. Last lesson of the week, feedback on final cuts and re-introduction to Evaluation questions.

19th March to 23rd March: 9am 19th March is Interim writing deadline. Lessons this week are for feedback on interim drafts and revisions/writing.


9am 26th March: Final writing deadline.